Feral Jundi

Tuesday, April 17, 2012

Legal News: DoS Statement On The Comprehensive Contingency Contracting Reform Act Of 2012

This is cool. Patrick Kennedy is commenting on this reform act, which will certainly have an impact on contracts with the government for future and current contingency operations. There is also a video of his testimony.

What is of interest is State’s concern of how this law would negatively impact the flexibility they require in order to deal with today’s problems. The Arab Spring is just one example of how quickly things can change out there. Here is the quote:

With regard to the automatic suspension provisions set out in proposed Section 113, we believe that the current, long-standing policy requiring a reasoned decision from the SDO based on a totality of information remains a sound approach, and would have concerns with a provision that imposes automatic suspension and debarment which will likely lead to due process challenges by the affected contractor community and potential court action that could delay necessary action in crisis situations.
Reorganization of Contracting Function (Sec. 131)
We respectfully do not concur with the re-organization of our contracting function proposed in Sec. 131. Defining the acquisition organization of the Department of State in statute would reduce our flexibility and codify the structure, making future adjustments to support new 21st century challenges cumbersome and time consuming. Future legislation would have to be drafted and passed to allow the Department to adjust to the fast changing world of diplomacy, rendering the Department less agile and thereby potentially handicapping the Department’s ability to respond to contingencies. Also, the proposed re-organization would constitute a bureau with not only the contracting function but logistics, motor vehicles, diplomatic pouch, household effects, shipping and storage. If a bureau were to be formed with only the contracting program, it would not be of sufficient size to warrant bureau-level status.

Probably the most relevant section of the statement to the readers of this blog was point about PSC’s and command and control. Here is the quote:

Private Security Contractors (Sec. 202)
The Department has a long history of using contract guards for protection of facilities and personnel stretching back to the 1970s, with enhanced capabilities in the 1990s. Private security contractors (PSCs) are critical to our readiness and capability to carry out American foreign policy under dangerous and uncertain security conditions. Maintaining this capability is particularly important when the Department is taking on expanding missions in contingency operations environments or areas that are transitioning from periods of intense conflict, such as in Iraq and Afghanistan.
That said, we appreciate the intent of section 202. We have sought to reduce risks associated with using contractors through robust oversight of our PSCs, as in CWC Recommendation 4. Contractors are operationally overseen and contractually managed by direct hire Department of State personnel, and we have instituted cultural training requirements, and contractor behavioral standards of conduct to ensure the professionalism of PSC personnel. The Department is staffed to properly oversee PSC compliance with these contractual requirements in Iraq and Afghanistan.
State strongly disagrees with the language of paragraph Sec. 202 (b)(1), which has the combatant commander determining whether performance of security functions by contractor personnel for the Department of State in overseas contingency areas is appropriate and necessary. This language is too open-ended and is not acceptable as it infringes upon the Secretary of State’s primary role in leading and carrying out foreign policy. The Secretary of State and the Chief of Mission have statutory responsibility for the safety and security of personnel under Chief of Mission authority. We routinely discuss the security situation in-country with DoD and other agencies present at post; and in situations where U.S. military forces are present, that coordination is intensified and ongoing. We fully comply with OFPP’s new Policy Letter on inherently governmental and critical functions, and our PSCs never engage in combat operations. We hope to work with you and your staff to find mutually acceptable language in this section.

What is interesting here is that 202 (b) (1) is a challenge to State’s control over their security force. It also causes confusion over who is really in charge of that force, which is not good in contingency operations.

If anything, the two groups should work together to ensure State’s security force is on the same sheet of music with the mission. Unity of effort is what should be the focus. But the language of this section is vague as to who is really in control of those forces. So I think State has a point here, but that is my personal opinion. Either way, check it out. –Matt

 

The Comprehensive Contingency Contracting Reform Act of 2012
Testimony
Patrick F. Kennedy
Under Secretary for Management
Statement before the Senate Committee on Homeland Security and Governmental Affairs Committee, Subcommittee on Contracting Oversight
Washington, DC
April 17, 2012
Good morning Chairman McCaskill, Senator Portman, and distinguished members of the subcommittee. Thank you for your invitation to appear here today to discuss Senate bill 2139, the Comprehensive Contingency Contracting Reform Act of 2012.
We share the Committee’s desire to ensure that efforts continue to strengthen contingency contracting. S. 2139 raises a number of important issues. While our review of the bill is ongoing, we welcome the opportunity to discuss our initial views on the bill’s provisions.
We understand that this legislation builds on the recommendations of the Commission on Wartime Contracting in Iraq and Afghanistan – an independent, bipartisan panel that you, Senator McCaskill, created along with Senator Webb in 2007. The State Department worked continuously with the Commission on Wartime Contracting (CWC) from when it was formed in early 2008 until it sunset last August, and gained valuable insight from the Commission’s efforts. We have taken many steps to improve our contingency contracting over the past several years, based on the CWC’s reports, recommendations from other oversight entities, and our own lessons learned.
The Department’s participation in CWC’s study was headed by the Office of the Under Secretary for Management and the Bureau of Administration. In addition to numerous meetings with the CWC, senior Department officials testified at seven formal CWC hearings.

(more…)